2021 Construction Projects

Current Road Construction

Wellington Road 18, at Beatty Line and at Gerrie Road
(Township of Centre Wellington)

Type of Work: Traffic signals and Intersection improvements

Timing: August 3 2021 to October 2021

Impact: A contractor has been hired to install traffic signals and complete intersection improvements on Wellington Road 18 at Beatty Line, and Wellington Road 18 at Gerrie Road.

No road closures are expected but there will be lane restrictions for all traffic at the two intersections between Elora and Fergus along Wellington Road 18.

Wellington Road 22, Culvert C221090 Replacement and Paving
(Township of Erin)

Type of Work: Culvert Replacement and paving

Timing: August 23, 2021 to October 2021

Impact: A contractor has been hired to complete a culvert replacement and paving located between Wellington Road 26 and Second Line.

There is a road closure on Wellington Road 22 between Wellington Road 26 and Second Line, with no through access.

A detour route is posted taking the travelling public around the project site.  The detour includes Wellington Road 26, Wellington Road 124 and Second Line. Delays are expected and the use of an alternative route is recommended.

Detour Route

Wellington Road 32, Culvert C320130 Rehab

(Township of Guelph/Eramosa) 

Type of Work: Culvert rehabilitation

Timing: July to November 2021

Impact: A contractor has been hired to complete a culvert rehabilitation of Culvert C320130 located between Highway 7 and Speedvale Avenue.

Lane restrictions are expected and additional information will be posted once determined. 

Completed Road Construction

Armstrong Bridge and Hagen's Bridge Replacements

Type of Work: Bridge replacement and rehabilitation

Timing: April 6 to October 2021

Impact: The road is now open and construction is complete.

Wellington Road 18, Bothwick Drain B018105 at Fifth Line, and Road Resurfacing from Fergus to Dufferin
(Township of Centre Wellington)

Type of Work: Bridge replacement and Asphalt Rehabilitation

Timing: June to Mid August, 2021

Impact: Construction is now complete.

Wellington Road 21, Badley Bridge B021057

(Township of Centre Wellington)

Type of Work: Bridge rehabilitation

Timing: Spring of 2021

Impact: Construction is now complete.

Wellington Road 29, Culvert C290110 Replacement

(Township of Centre Wellington)

Type of Work: Culvert Replacement

Timing: August 16 2021 (weather depending)

Impact: Construction is now complete.

Wellington Road 30, from Wellington Road 39 to Wellington Road 86 
(Township of Guelph/Eramosa)

Type of Work: Asphalt rehabilitation

Timing: June to September 2021

Impact: Road is now open and construction is complete.

Wellington Road 32, Culvert C321140 Replacement
(Township of Puslinch)

Type of Work: Culvert replacement

Timing: August 30, 2021 to October 19, 2021

Impact: Road is now open and construction is complete.

Wellington Road 37 - Arkell Road 

(Township of Puslinch)

Type of Work: Asphalt Restoration

Timing: September 20 to 24, 2021

Impact: Construction is now complete.

Wellington Road 46 (Brock Road), from Maltby Road to McLean Road West

(Township of Puslinch)

Type of Work: Road construction (Phase II) - Paving

Timing: Until the end of June, 2021

Impact: Construction is now complete.

Wellington Road 109, Maitland River Bridge B109128
(Town of Minto)

Type of Work: Bridge rehabilitation

Timing: April 19 to mid July, 2021

Impact: Road is now open, construction is complete.

Wellington Road 109, Mallet River Bridge B109129
(Township of Wellington North)

Type of Work: Bridge rehabilitation

Timing: April 5 to mid July, 2021

Impact: Road is now open, construction is complete.

Wellington Road 109, at Sideroad 15, Bridge B109141
(Township of Wellington North)

Type of Work: Bridge rehabilitation

Timing: June 23 to July 16, 2021

Impact: The road is now open, construction is complete.

Wellington Road 109, Microsurfacing 
(Township of Wellington North)

Type of Work: Microsurfacing

Timing: September 7 to September 17, 2021

Impact: Construction is now complete.

Miscellaneous Road Projects

Wellington Road 29, at Highway 7
(Township of Guelph-Eramosa)

Type of Work: Railway crossing improvements completed by Metrolinx

Timing: Saturday October 30th and Sunday October 31st, 2021

Impact: Please be advised that Wellington Road 29 will be closed at Highway 7 for railway crossing improvements to be completed by Metrolinx.

Please use the provided detour route for the project.

Detour Route

Main Street South Closure (Highway 7) Rockwood, between Harris Street and Frederick Street (Township of Guelph-Eramosa)

Type of Work: Railway track repairs and paving

Timing: August 3, 2021 to approximately September 2021

Impact: Construction is now complete.

Wellington Road 11, between 4th Line and Wellington Road 45
(Mapleton Township)
Type of Work: Inspection and service work

Timing: September 27 until October 8, 2021 between 9:00 am and 3:00 pm

Impact: Construction is now complete.

Wellington Road 24 (Trafalgar Road), between Side Road 27 and Erin-Garafraxa Townline
(Town of Erin)

Type of Work: Entrance improvements to Hillsburgh Pit

Timing: September 27, 2021 for approximately 7 weeks

Impact: Please be advised Wellington Road 24 (Trafalgar Road), between Side Road 27 and Erin-Garafraxa Townline, in the Town of Erin will be reduced to a single lane of traffic during working hours beginning Monday, September 27, 2021 for approximately 7 weeks. The project includes localized roadway improvements and culvert installation.

Two-way traffic will be maintained during working hours by flagpersons and all lanes will be open outside of working hours. All local residences and businesses will remain accessible during the project.

Delays are expected and the use of an alternative route is recommended.

Project Location

Wellington Road 7, between David Street and Wellington Road 21
(Township of Centre Wellington) 

Type of Work: Installation of municipal services for new development

Timing: May 10 to July, 2021

Impact: Construction is now complete.

Wellington Road 34, from First Line Nassagaweya to Watson Road South
(Township of Puslinch)

Type of Work: Railway track repairs and paving

Timing: June 4, 2021 at 6:00 pm to June 5, 2021 at 5:00 pm

Impact: The road is now open and construction is complete.

© 2021 County of Wellington, 74 Woolwich St. Guelph, Ontario N1H 3T9, T 519.837.2600, TF 1.800.663.0750, F 519.837.1909